Dated : June 11, 2024
CHENNAI: The Chennai Corporation will renovate 1.2 km of the road, at a cost of ₹36 crore; parking spaces below the flyover and designated spots for school crossings are some of the facilities that will come up.
The Greater Chennai Corporation (GCC) is planning to renovate a 1.2-km stretch of the Tiruvottiyur High Road under the Special Projects Department, by adding several features.
The 10-km arterial road connects the Manali High Road and Washermanpet railway station. Earlier, a 2.4 km of the stretch was restored after the Corporation constructed the stormwater drain last year.
The latest project is planned under the Sustainable Urban Services Programme (SUSP), at a cost of ₹36 crore. After administrative sanction was obtained, the project has been tendered out for implementation, civic officials said.
Parking spaces below the flyover between the pillars, designated zones for school crossings, pavements, and stormwater drain links have been planned. Greenery, such as vertical gardens watered through drip irrigation, similar to the ones placed under the flyovers on Cathedral Road and across Chamiers Road, are also coming up.
Further, in phase II of the SUSP implementation, the remaining 1.8-km stretch of the 3-km-long Tiruvottiyur High Road, will be improved with parks, traffic islands, green zones, bollards, footpaths and better streetlights.
This proposal was presented during a two-day workshop in May, conducted by the Institute for Transportation and Development Policy (ITDP), for officials and engineers of the GCC.
At present, debris has been dumped under the flyover between the medians, there is irregular parking and there are no pavements on the road, the presentation revealed.